Connect with us

Business

PenCom Extends Pension Verification Deadline for Civil Servants to December 2026

info

Published

on

The National Pension Commission (PenCom) has extended the deadline for the ongoing mandatory One-Time Online Verification and Enrolment Exercise for employees of treasury-funded Ministries, Departments and Agencies (MDAs) who are entitled to accrued pension rights.

The exercise, which started in February 2026 and was initially scheduled to end on 31 July 2026, has now been extended to 31 December 2026. The extension follows several requests from MDAs seeking additional time for employees to participate in the online enrolment process.

The extension provides all eligible employees with another opportunity to complete the exercise and ensure that their accrued pension rights are accurately determined ahead of retirement.

Deadline Extension Due to Low Participation

Low participation in the exercise has necessitated the timeline extension. As at July 2026, MDAs had uploaded 62,320 records of active employees and retirees, while only 31,099 employees had successfully completed the enrolment process.These figures fall short of an estimated 150,000 active Federal Government employees entitled to accrued pension rights.

PenCom is therefore urging all eligible employees who are yet to enrol, as well as those who have started but not completed the process, to use the additional time provided by the extension to complete their enrolment.

Exercise Addresses Legacy Pension Liabilities

The initiative is part of the Federal Government’s efforts to settle pension liabilities carried over from the Defined Benefit Scheme (DBS), which existed before the introduction of the Contributory Pension Scheme (CPS) in 2004.

Under Section 15(1) of the Pension Reform Act 2014 (PRA 2014), employees who transited to the CPS are entitled to accrued pension rights, beingbenefits earned under the DBS.

These accrued rights comprise pension and gratuity benefits earned by eligible employees from their date of first appointment up to 30 June 2004. Their determination is based on an actuarial valuation process.

In a circular issued on 27 April 2026, the Head of Civil Service of the Federation had directed all treasury-funded MDAs to support the exercise and ensure that eligible employees complete the One-time Enrolment as required by PenCom. This is essential for determining the Federal Government’s outstanding pension liabilities and making adequate budgetary provisions for their settlement.

Digital Transformation Drives New Approach

The One-Time enrolment exercise is fully digital and is conducted through PenCom’s Contributions and Bond Redemption Application (COBRA).

COBRA is a secure platform designed to facilitate data capture, validation and processing.

Benefits of Early Enrolment

Early completion facilitates the determination of accrued pension rights and enables the necessary funding to be secured from the Federal Government. Subsequently, the amounts would be credited to the employees’ Retirement Savings Accounts (RSAs) well ahead of retirement, thereby earning investment returns and boosting retirement benefits.

MDAs, Pension Desk Officers and PFAs Have Key Roles

MDAs are required to upload details of eligible employees on the COBRA platform, after which affected employees are expected to visit their respective Pension Fund Administrators (PFAs) with the required documents to complete the enrolment process.

Pension Desk Officers (PDOs), who have been trained by PenCom, coordinate the exercise within their organisations and guide employees through the process.

PenCom continues to collaborate with MDAs, PFAs and other stakeholders to improve awareness, facilitate participation and ensure that eligible employees are properly captured.

PenCom Urges Eligible Employees to Act

While the extension to 31 December 2026 provides additional time, PenCom has urged eligible employees and their respective MDAs not to delay completion of the process. All active employees of Federal Government Treasury-funded MDAs who were in service as at 30 June 2004 are covered by the accrued pension rights provisions.

PenCom therefore calls on all eligible employees and Treasury-funded MDAs to take full advantage of the extension and complete the enrolment exercise before the new deadline.

The post PenCom Extends Pension Verification Deadline for Civil Servants to December 2026 appeared first on Business Today NG.

Continue Reading
Click to comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Business

Communications Ministry made ₦345.5 million duplicate payment for Abuja ICT Park project

info

Published

on

I commend a distinguished Leader Boss and Head of the Supreme Audit Institution of Nigeria SAI e1791.jpeg

The Auditor-General of the Federation flagged an alleged ₦345.5 million duplicate payment by the Federal Ministry of Communications, Innovation, and Digital Economy to a contractor handling the Abuja ICT Park project.

The finding was contained in the Auditor-General’s Annual Report on Non-Compliance and Internal Control Weaknesses in Ministries, Departments and Agencies of the Federal Government for the year ended 31 December 2024.

The special audit of the communication ministry covered the period from 1 January to 31 December 2021 and raised 14 issues concerning the planning, funding, procurement and implementation of the ICT Park project.

At the time the project was being implemented, Isa Ali Pantami, who was appointed by former President Muhammadu Buhari, served as Minister of Communications and Digital Economy from 2019 to 2023. He was succeeded by Bosun Tijani, who was appointed by President Bola Tinubu.

₦345.5 million duplicate payment

In Issue 13 of the findings, titled “Loss of Fund Due to Duplicated Payments to Contractor,” the Auditor-General said the ministry processed and approved two separate payments of ₦345,499,262.74 each as the third tranche of the 15 per cent mobilisation advance to the contractor.

The payment was intended to establish the Information and Communication Technology (ICT) Park, Abuja.

PT WHATSAPP CHANNEL
Dangote Refinery AD

The Permanent Secretary approved the first payment on 19 January 2022 through payment voucher No. FMCDE/CAP/606/2021 dated 24 January 2022.

The same accounting officer approved the second payment on 17 January 2023 through payment voucher No. FMCDE/CAP/149/2022 dated 8 February 2023.

The report said the two paid vouchers had identical contract references, amounts, and narrative descriptions, which it said indicated duplicate payment.

It added that no record showed the first payment had been reversed, adjusted, or treated as an accounting error.

“There was also no journal entry, refund, or internal memo linking the 2023 approval to any prior transactions. These omissions demonstrate a failure of supervisory review, record reconciliation, and payment verification within the Ministry,” the findings stated.

The Finance and Accounts Department also failed to justify the repeated authorisation or the lack of reconciliation between the Cash Book and Vote Book, according to the report.

The findings said the contractor, while claiming it received only one payment in 2023, submitted a bank statement that excluded the critical period between 2 January 2022 and 8 February 2023, preventing independent verification of its claim.

The audit said the payments posed risks of fund diversion and loss of public funds, attributing this to weaknesses in the ministry’s internal control system.

The audit said the ministry’s management did not respond to the alleged duplicate payment under the contract.

The Auditor-General recommended that ₦345.499 million be recovered and remitted to the Treasury, and that evidence of remittance be forwarded to the Public Accounts Committee of the National Assembly.

₦447.67m from undisclosed funding sources

In Issue 11, the auditors questioned ₦447.67 million in payments to the ICT Park contractor, which they said could not be traced to the Government Integrated Financial Management Information System (GIFMIS).

The amount comprised ₦102,166,730 and ₦345,499,262.74 paid to the contractor, vide paid vouchers, Ref. No. FMCDE/CAP/061/2021 and FCMDE/606/2022 on 11 June 2021 and 19 February 2022, respectively.

According to the report, the payments appeared in the cash book. The contractor acknowledged them in the progress report and bank statement, but they did not appear in GIFMIS records, indicating they were processed off the system.

The audit said officials in the ministry’s Finance and Accounts Department could not explain the existence or authorisation of the alternative funding sources.

The report said the ministry also failed to provide documentation showing lawful appropriation, supplementary approval, or an external funding agreement for the payments.

The audit said the action posed a risk of misappropriation of funds and diversion of public property.

It said the ministry’s management did not respond to questions about the history of the payments in the GIFMIS records.

The Auditor-General recommended recovering and remitting ₦447.67 million to the Treasury, with sanctions under paragraphs 3106 and 3129 of the Financial Regulations (2009) if the ministry fails to comply.

₦396.65 million project funds used for unrelated items

In Issue 9, the findings showed that N396.65 million from the ICT Park project fund was used to pay for consultancy services, office consumables, furniture, and stationery printing.

The audit said approvals had been processed for consultancy services relating to the ICT Park. Still, payments were made to unrelated suppliers for consumables and office furniture that were not contained in the project’s Bill of Quantities.

The report said this reduced funds meant for the mobilisation and execution of the ICT Park project.

It also said the ministry failed to provide evidence of approval for the virement from the Minister of Finance, Budget and National Planning and the National Assembly.

It said the actions posed a risk of misappropriation of funds and undue delay in completion of the project, noting that the ministry failed to respond to the question on the use of the project funds for unrelated items.

The Auditor-General recommended recovering and remitting ₦396.655 million to the Treasury, with sanctions under paragraphs 3106 and 3129 of the Financial Regulations (2009) if the ministry fails to comply.

₦1.85bn paid without performance bond

In Issue 10, the auditors also found that N1.848 billion was paid to the contractor without securing a valid Performance Bond.

The report said the Bureau of Public Procurement had directed in December 2020 that a minimum 10 per cent Performance Bond be secured for major contracts before payment of mobilisation fees.

However, the ministry first released ₦1.348 billion in mobilisation payments between March 2021 and February 2023 without obtaining the required bond.

The report said that nearly three years after the contract award, the contractor submitted a commitment letter dated 29 December 2023, promising to furnish a Performance Bond upon receiving an additional N500 million. This amounts to ₦1.848 billion.

It said the actions exposed public funds to loss, noting that the ministry failed to respond to the question on the payment.

The Auditor-General recommended recovering and remitting ₦1.848 billion to the Treasury, and imposing sanctions under paragraphs 3106 and 3129 of the Financial Regulations (2009) if the ministry fails to comply.

₦500 million paid without interim performance certificate

In Issue 12, the Auditor-General said the ministry released an additional ₦500 million to the contractor on 29 December 2023 without an Interim Performance Certificate or verified progress report.

The report said the payment was made after the contractor received the 15 per cent mobilisation fee.

Instead of an Interim Performance Certificate, the ministry relied on a commitment letter from the contractor promising to provide project vehicles and undertake overseas technical trips upon receipt of the additional funds.

The audit said the actions posed a risk of diverting public funds and losing government funds. It said that the ministry failed to respond to the question on the payment.

The Auditor-General recommended recovering and remitting N500 million to the Treasury and imposing sanctions under paragraph 3106 of the Financial Regulations (2009) if the ministry fails to comply.

Premature foreign trips of ₦90 million

In Issue 8, the auditors questioned a ₦90 million provisional sum for foreign trips to inspect technical equipment for the ICT Park.

According to the findings, the sum of ₦90 million was included and described as “Allow a provisional sum of N90 million to cater for Client’s and Consultants’ representatives for foreign trips for the inspection of technical equipment to be deployed for the project,” in the priced Bill of Quantities (BOQ) for the contract for the ICT Park project, with a contract sum of ₦8.984 billion.

The report said the expenditure was being planned while the project was still at foundation level, before structural works, equipment procurement or installation had commenced.

It said no evidence was provided to justify the technical need, approved schedule, or cost-benefit assessment supporting the timing of the proposed trips.

The audit said the action demonstrated weak expenditure prioritisation and poor sequencing of project activities, noting that it posed a risk of undue delay in completion of the project and diversion of public funds.

Again, the ministry did not respond to questions about the premature foreign trip.

The Auditor-General recommended recovering and remitting the N90 million. It also recommended sanctions under paragraphs 3106 and 3115 of the Financial Regulations (2009) if the ministry fails to comply.

Denial of access to project documents

The audit also raised concerns about the ministry’s failure to give auditors access to project documents.

In Issue 14, the report said auditors were denied access to documents including needs assessment reports, bank mandates for ICT project payments, payment vouchers, due diligence reports on the contractor and the Environmental and Social Impact Assessment report.

READ ALSO: How Nigeria’s Population Commission mismanaged N245 billion on undelivered products, other controversial contracts – Auditor-General

The report said several requests for project-related documents made between March and June 2025 were not answered by the ministry.

It said the denial of access to procurement documents contravened the Constitution and risked concealing financial information, diverting government revenue, and the loss of public funds.

The Auditor-General asked the Permanent Secretary to justify the denial of access and produce all documents relating to the ICT Park project.

The report stated that the ministry did not respond to the issues raised in the audit and that the findings remained valid until the recommendations were implemented.

Other issues

Other issues included a ₦94.05 million cost overrun attributed to the failure to conduct feasibility studies and an Environmental Impact Assessment before the ICT Park project began.

The Auditor-General also flagged ₦19.47 million in costs linked to delayed site handover, while questioning the absence of resident technical supervision despite a ₦160 million provision for it.

The report further cited inadequate budgetary provisions that contributed to project delays and the ministry’s failure to conduct or document a needs assessment before procurement.


Discover more from Premium Times Nigeria

Subscribe to get the latest posts sent to your email.

Continue Reading

Business

Lasaco Assurance Gets Approval to Offer Agricultural Insurance, Eyes Higher Revenue

info

Published

on

BY NKECHI NAECHE-ESEZOBOR—Lasaco Assurance Plc has secured regulatory approval to underwrite agricultural risks, expanding its product portfolio and positioning the insurer for higher revenue as it taps opportunities in the agricultural value chain.

Under the approval the company  will offer Multi-Perils Crop Insurance, Plantation Insurance, Poultry Farm Insurance, Fishery Insurance, Livestock Insurance, Farm Property and Produce Insurance, and Cattle Insurance.

As part of its agricultural insurance offerings, it will provide a comprehensive range of products designed to support farmers and stakeholders across the sector.

Agriculture continues to be a vital driver of Nigeria’s economic development, sustaining livelihoods, contributing significantly to food production, and creating business opportunities nationwide.

The availability of tailored agric  products through reputable financial institutions plays a crucial role in meeting the risk management needs of farmers, agribusinesses, and other sector participants.

Mr Ademoye Shobo the Managing Director, expressed confidence that this approval will substantially boost the company’s revenue going forward.

He  emphasized that it presents a valuable opportunity for Lasaco Assurance to contribute meaningfully to the protection and growth of this niche market.

While Mr. Adedayo Adetokun, Head of Strategy, highlighted that this development aligns perfectly with the company’s long-term vision to deepen sectoral diversification and strengthen its competitive positioning.

He noted that leveraging strategic partnerships and innovative approaches will be key to maximizing the potential of the agricultural insurance portfolio.

With this authorization, Lasaco Assurance is well-positioned to advance its agricultural insurance business in full compliance with regulatory requirements.

The company anticipates forging stronger relationships with agricultural enterprises, distributors, farmers, and other stakeholders, thereby gaining deeper insights into market dynamics and identifying sustainable growth opportunities.

This milestone signals a new phase in Lasaco Assurance Plc’s business trajectory, enhancing its engagement within Nigeria’s agricultural market and setting the stage for continued expansion and value creation.

The post Lasaco Assurance Gets Approval to Offer Agricultural Insurance, Eyes Higher Revenue appeared first on Business Today NG.

Continue Reading

Trending